HomeMy WebLinkAbout2024-06 Citywide Misc Concrete Improvements Engineer's EstimateProject No. 2024-06
Citywide Miscellaneous Concrete Improvements
Item
No.Description QTY Unit Unit Price Extended Price
1 MOBILIZATION 1 LS $ 10,000.00 10,000.00$
2 TRAFFIC CONTROL 1 LS $ 10,000.00 10,000.00$
3 DUST CONTROL 1 LS $ 4,000.00 4,000.00$
4 SAWCUT, REMOVE, AND DISPOSE OF EXISTING CURB & GUTTER; AND/OR ROLLED CURB 120 LF $ 35.00 4,200.00$
5 SAWCUT, REMOVE, AND DISPOSE OF EXISTING SIDEWALK, RAMP, DRIVEWAY, AND
CROSS-GUTTER 840 SF $ 8.00 6,720.00$
6 CONSTRUCT 6" CURB & GUTTER PER CITY OF LA QUINTA STD. 201, 3" DOWEL INTO
ADJACENT EXISTING CONCRETE CURB 50 LF $ 65.00 3,250.00$
7 CONSTRUCT TYPE 'C' CURB PER CITY OF LA QUINTA STD. 203, 3" DOWEL INTO ADJACENT
EXISTING CONCRETE CURB 40 LF $ 75.00 3,000.00$
8 CONSTRUCT CURB TRANSITION PER CITY OF LA QUINTA STD. 205, 3" DOWEL INTO
ADJACENT EXISTING CONCRETE CURB 10 LF $ 150.00 1,500.00$
9 CONSTRUCT CONCRETE DRIVEWAY PER CITY OF LA QUINTA STD. 221 MOD 220 SF $ 25.00 5,500.00$
10 CONSTRUCT PORTION OF CROSS-GUTTER PER CITY OF LA QUINTA STD. 230 & 231 MOD. 30 SF $ 40.00 1,200.00$
11 CONSTRUCT SIDEWALK PER CITY OF LA QUINTA STD. No. 240 MOD. 380 SF $ 11.00 4,180.00$
12 CONSTRUCT CONCRETE CURB RAMP PER CITY OF LA QUINTA STD. No. 250 MOD., CASE B
(INCLUDING CURB AND GUTTER ALONG RAMP)1 EA $ 6,000.00 6,000.00$
13 CONSTRUCT CONCRETE CURB RAMP PER CITY OF LA QUINTA STD. NO. 250 MOD., CASE
E (INCLUDING CURB AND GUTTER ALONG RAMP)1 EA $ 5,000.00 5,000.00$
14 SAWCUT, REMOVE, AND DISPOSE OF EXISTING CONCRETE RAMP; FURNISH AND
INSTALL TRUNCATED DOME CONCRETE TILE PER CITY OF LA QUINTA STD. 250 MOD.40 SF $ 105.00 4,200.00$
15 FULL DEPTH GRIND ASPHALT CONCRETE PAVEMENT (4"), COMPACT EXISTING BASE,
AND VARIABLE OVERALY (4" - 5")570 SF $ 36.00 20,520.00$
16 GRADE PARKWAY, REMOVE, MODIFY, AND REPLACE LANDSCAPE, HARDSCAPE, AND
IRRIGATION IN KIND TO FURTHEST EXTENT POSSIBLE 1 LS $ 5,000.00 5,000.00$
17 STRIPING AND PAVEMENT MARKINGS, INCLUDING ALL INCIDENTALS 1 LS $ 7,000.00 7,000.00$
101,270.00$
Engineer's Estimate
Total Amount of Bid Items 1 – 17:
4/10/2026 Page 1 of 1