2023 Ortiz Enterprises - Project 2011-05 Dune Palms Bridge - Change Order No. 6ta 0"fra GEM ofibe DESERT - TO: Jon McMillen, City Manager FROM: Bryan McKinney, P.E., Public Works Director/City Engineer Via: Carley Escarrega, Management Assistant DATE: February 15, 2024 RE: Contract Change Order No. 6 Dune Palms Road Bridge Project No. 2011-05 Attached for your signatures is one (1) electronic Contract Change Order No. 6 between Ortiz Enterprises, Inc. and the City of La Quinta for the project referenced above. DESCRIPTION OF CHANGE This Contract Change Order allows for CVWD Final tie-in Total $65,798.73 Please sign and return the original to the City Clerk for final distribution. REQUESTING DEPARTMENT TO CHECK THE ITEMS BELOW AS APPROPRIATE: X Contract payments will be charged to the construction account number: 401-0000-60188-111205-CT Authority to execute this agreement is based upon: City Manager's signature authority provided under Resolution No. 2019-021 for budgeted expenditures of $50,000 or less. _X_ City Council approval on October 18, 2022 The following Budget Summary is provided: Project Budget $ 29,756,245 Contract Amount ($ 21,635,759.60) Change Order No. 1 - 5 ($ 190,927.79) This Contract Change Order No. 6 ($ 65,798.73) Balance Remaining $ 7,863,758.88 As indicated, adequate funding is available. 78-495 Calle Tampico La Quinta, CA 92253 760.777.7000 - CALIFORNIA - Sheet 1 of 2 CONTRACT: Dune Palms Road Bridge Improvement Project PROJECT #: 2011-05 CONTRACTOR: ORTIZ ENTERPRISES, INC. 6 Cushing Suite 200 Irvine, CA 92618-4221 CONTRACT CHANGE ORDER NO. 006 Pursuant to the terms of the original Contract Agreement, you are hereby directed to make the herein described changes or do the following described work not included in the plans and specifications for this Contract. Unless otherwise stated all work shall conform to the terms, general conditions, and special provisions of the original Contract. DESCRIPTION OF CHANGE Per direction of the Coachella Valley Water District, the preexisting abandoned waterline in the channel on the east side of Dune Palms Road was removed from abutment 1 to abutment 5. This work was performed at an agreed bid item price of $ 98/LF for 480 LF length. Total cost of $ 47,040.00 CVWD final tie-in work at the north and south connection point was performed by SRK forces, under CVWD direction. CVWD required extra thrust blocks to be placed at the blind flange locations. This work was tracked on a time and material basis and covered as Extra Work at Force Account. Cost for the three days of work for SRK was $ 17,865.46. Ortiz 5 % markup made this total cost $ 18,758.73. Total $ 65,798.73 After review of tentative work agreements and invoices from the force account work, the agreed lump sum price of $ 65,798.73 was determined. Price total will constitute full and complete compensation, including markups for construction work and delays incurred. Current Contract Amount $ 21,817,687.39 Add This Change Order No. 006 $ 65,798.73 Revised Contract Total $ 21,883,486.12 t_ 78495 Calle Tampico I la Ouinta, California 922531760.777.70901 www.laquintaca.gov W �GNNW CAU1 ORNIA - By reason of this contract change order the time of completion is adjusted as follows: - 0 - days added to contract time. The contract completion date shall be: 02/06/2025 �7 Submitted By: Approved By: Date: Date: February 23, 2024 We, the undersigned Contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all materials, perform all labor, except as may be noted above, and perform all services necessary to complete the above specified work, and hereby accept as full payment the amount shown Accepted By: Contractor: Title: Date: 2 ��� 2011-05 CCO 6 Final Audit Report Created: 2024-02-15 By: Carley Escarrega (cescarrega@laquintaca.gov) Status: Signed Transaction ID: CBJCHBCAABAAEFhAQdgis871MVwOilJlwi841PH8YuRE "2011-05 CCO 6" History Document created by Carley Escarrega (cescarrega@laquintaca.gov) 2024-02-15 - 10:15:56 PM GMT- IP address: 24.30.141.148 Document emailed to Ubaldo Ayon (uayon@laquintaca.gov) for signature 2024-02-15 - 10:16:01 PM GMT 2024-02-15 Document emailed to Bryan McKinney (bmckinney@laquintaca.gov) for signature 2024-02-15 - 10:16:01 PM GMT Email viewed by Ubaldo Ayon (uayon@laquintaca.gov) 2024-02-15 - 10:19:38 PM GMT- IP address: 104.47.65.254 E1 Document e-signed by Ubaldo Ayon (uayon@laquintaca.gov) Signature Date: 2024-02-15 - 10:19:46 PM GMT - Time Source: server- IP address: 47.176.173.154 Email viewed by Bryan McKinney (bmckinney@laquintaca.gov) 2024-02-15 - 11:22:25 PM GMT- IP address: 104.47.65.254 E1 Document e-signed by Bryan McKinney (bmckinney@laquintaca.gov) Signature Date: 2024-02-15 - 11:22:53 PM GMT - Time Source: server- IP address: 47.176.173.154 Agreement completed. 2024-02-15 - 11:22:53 PM GMT a Adobe Acrobat Sign